Central West Ambulance Stations
Solar System Installation
CLIENT
NSW Ambulance
SERVICE
Solar
LOCATION
Multiple sites across Central West, NSW
TIMELINE
3 months
PROJECT INFORMATION
Platinum Electricians were responsible for the the design and installation of solar systems on a number of Ambulance Stations across Central West NSW:
- Bathurst - 40kW
- Orange - 20kW
- Dubbo - 20kW
- Lithgow - 20kW
- Molong - 15kW
Each solar system utilises SMA inverters and Trina panels, and are monitored using Solar Analytics. This also helps with planning for maintenance and cleaning.
The key objective of this project was energy reduction and bill minimisation across NSW Health, all whilst increasing the renewable usage for Government Departments.

OBJECTIVES & PRIORITIES
Energy
Reduction
Reduction

Fit for Purpose
(compliant)
(compliant)

Quality
Workmanship
Workmanship
Cost
Savings
Savings
KEY ACHIEVEMENTS
- System design and installation
- Energy reduction
- Cost savings across NSW Health
- Management of Small-scale Technology Certificates (STCs)
- After-care service and maintenance
PROJECT VALUE
$150k - $200k
RECENT PROJECTS

TOUCH
ST CATHERINE'S
AGED CARE Power, Lighting & Data Upgrades

TOUCH
CENTRAL WEST
AMBULANCE STATIONS Solar System Installation

TOUCH
WARRUMBUNGLE
VISITOR CENTRE Fit Out & Solar

TOUCH
CENTRAL WEST Specialised Industrial & Mining